Aptitude | Wipro Mock Test | Question 40
Mira and Ram can do a piece of work in 6 and 9 days respectively; If they work on alternate days starting with Mira on the first day. How many days will be taken to complete work?
(A) 6
(B) 7
(C) 8
(D) 9
Answer: (B)
Explanation:
Quiz of this Question
Please comment below if you find anything wrong in the above post
Recommended Posts:
- Aptitude | Wipro Mock Test | Question 24
- Aptitude | Wipro Mock Test | Question 4
- Aptitude | Wipro Mock Test | Question 5
- Aptitude | Wipro Mock Test | Question 6
- Aptitude | Wipro Mock Test | Question 7
- Aptitude | Wipro Mock Test | Question 8
- Aptitude | Wipro Mock Test | Question 9
- Aptitude | Wipro Mock Test | Question 10
- Aptitude | Wipro Mock Test | Question 16
- Aptitude | Wipro Mock Test | Question 39
- Aptitude | Wipro Mock Test | Question 17
- Aptitude | Wipro Mock Test | Question 35
- Aptitude | Wipro Mock Test | Question 18
- Aptitude | Wipro Mock Test | Question 19
- Aptitude | Wipro Mock Test | Question 13