The current erection cost of a structure is Rs. 13,200. If the labour wages per day increase by 1/5 of the current wages and the working hours decrease by 1/24 of the current period, then the new cost of erection in Rs. is
(A) 16,500
(B) 15,180
(C) 11,000
(D) 10,120
Answer: (B)
Explanation: Cost is proportional to wages per day and number of hours.
Wages are increased by 1/5 and working hours are decreased by 1/24.
So the cost becomes (current cost)*(1+1/5)*(1-/24) = 13200*(6/5)*(23/24) = 15180
Quiz of this Question
Recommended Posts:
- GATE | GATE CS 2013 | Question 1
- GATE | GATE CS 2013 | Question 2
- GATE | GATE CS 2013 | Question 3
- GATE | GATE CS 2013 | Question 4
- GATE | GATE CS 2013 | Question 65
- GATE | GATE CS 2013 | Question 6
- GATE | GATE CS 2013 | Question 7
- GATE | GATE CS 2013 | Question 8
- GATE | GATE CS 2013 | Question 65
- GATE | GATE CS 2013 | Question 65
- GATE | GATE CS 2013 | Question 11
- GATE | GATE CS 2013 | Question 12
- GATE | GATE CS 2013 | Question 13
- GATE | GATE CS 2013 | Question 14
- GATE | GATE CS 2013 | Question 15
- GATE | GATE CS 2013 | Question 65
- GATE | GATE CS 2013 | Question 17
- GATE | GATE CS 2013 | Question 18
- GATE | GATE CS 2013 | Question 19
- GATE | GATE CS 2013 | Question 65