The correct matching for the following pairs is
A. Activation record 1. Linking loader B. Location counter 2. Garbage collection C. Reference counts 3. Subroutine call D. Address relocation 4. Assembler
(A) A-3, B-4, C-1, D-2
(B) A-4, B-3, C-1, D-2
(C) A-4, B-3, C-2, D-1
(D) A-3, B-4, C-2, D-1
Answer: (D)
Explanation: