P and Q can do a work in 30 and 60 days respectively. They agreed to work together and finish the work for 1000 Rupees. But they worked only for 10 days. How much money should they together get ?
(A) 500
(B) 100
(C) 800
(D) 200
Answer: (A)
Explanation: one day combined work of P and Q= 1/30+1/60 = 1/20.
Thus P and Q can finish the work together in 20 days.
But they have worked only for 10 days which means they have finished half of the job.
So they will be paid half of the money= 500 rs
Quiz of this Question
Recommended Posts:
- GATE | GATE MOCK 2017 | Question 1
- GATE | GATE MOCK 2017 | Question 2
- GATE | GATE MOCK 2017 | Question 3
- GATE | GATE MOCK 2017 | Question 4
- GATE | GATE MOCK 2017 | Question 5
- GATE | GATE MOCK 2017 | Question 7
- GATE | GATE MOCK 2017 | Question 8
- GATE | GATE MOCK 2017 | Question 9
- GATE | GATE MOCK 2017 | Question 10
- GATE | GATE MOCK 2017 | Question 11
- GATE | GATE MOCK 2017 | Question 12
- GATE | GATE MOCK 2017 | Question 13
- GATE | GATE MOCK 2017 | Question 14
- GATE | GATE MOCK 2017 | Question 15
- GATE | GATE MOCK 2017 | Question 16
- GATE | GATE MOCK 2017 | Question 17
- GATE | GATE MOCK 2017 | Question 18
- GATE | GATE MOCK 2017 | Question 19
- GATE | GATE MOCK 2017 | Question 20
- GATE | GATE MOCK 2017 | Question 21