Early Design Model : COCOMO-II

Last Updated : 28 Sep, 2020
Summarize
Comments
Improve
Suggest changes
Like Article
Like
Save
Share
Report
News Follow

It is used at the Stage – II in COCOMO -II models and supports estimation in early design stage of project. Base equation used in COCOMO – II models is as follows –

PMnominal = A * (size)B 
where PMnominal = Effort for the project in person months
A = constant representing the nominal productivity where A = 2.5
B = Scale Factor
Size = size of the Software

The early design model uses Unadjusted Function Points (UFP) as measure of size. This model is used at the early stages of software project when there is not enough information available about size of product which has t be developed, nature of target platform and nature of employees to be involved in development of projector detailed specifications of process to be used. This model can be used in either Application Generator, System Integration, or Infrastructure Development Sector.

If B = 1.0, there is linear relationship between effort and size of product. If the value of B is not equal to 1, there will be non-linear relationship between size of product and effort. If B < 1.0, rate of increase of effort decreases as the size of product increases. If B > 1.0, rate of increase of effort increase as the size of product is increased.

This is due to growth of interpersonal communications and overheads due to growth of large system integration. Application composition model assumes value of B equal to 1. But Early Design Model assumes value of B to be greater than 1.

Thus here the basic assumption stands as effort on project usually increases faster than size of product. However, value of ‘B’ is computed on basis of scaling factors that may cause loss of productivity corresponding to an increase in the size as follows –

  1. Precedentness :
    It reflects the experience on similar projects previously. This is applicable to individuals as well as organizations both in terms of expertise and experience. High value would imply that organization is quite familiar with application formula and very low value means no previous experience or expertise. The value for scale factor is 6.20(Very Low), 4.96(Low), 3.72(Average), 2.48(High), 1.25(Very High) and 0.00(Extra High).

  2. Development Flexibility :
    It reflects degree of flexibility in development process. Low value would imply well defined process being used. Very high value would imply that the client offers very general idea of the product or project. Value for the scale factor is 5.07(Very Low), 4.05(Low), 3.04(Average), 2.03(High), 1.02(Very High) and 0.00(Extra High).

  3. Architecture Risk and Resolution :
    It represents degree of risk analysis being carried out during course of project. Low value would indicate little analysis and very high value would represent complete and thorough risk analysis. Value for the scale factor is 7.07(Very Low), 5.65(Low), 4.24(Average), 2.83(High), 1.41(Very High) and 0.00(Extra High).

  4. Team Cohesion :
    Reflects the team management skills of the employees developing the project. Very low value would imply very low interaction and hardly any relationship among the members however high value would imply great relationship and good team work. The value for scale factor is 5.48(Very Low), 4.38(Low), 3.29(Average), 2.19(High), 1.10(Very High) and 0.00(Extra High).

  5. Process maturity :
    Reflects process maturity of organization. Very low value would imply organization has no level at all and high value would imply that organization is rated as highest level of the SEI-CMM. The value for scale factor is 7.80(Very Low), 6.24(Low), 4.68(Average), 3.12(High), 1.56(Very High) and 0.00(Extra High).
The value of B can be calculated as -
B = 0.91 + 0.01 * (Sum of rating scaling factors for project)

When all scaling factors of project are rated as extra high, best value of B is obtained which is equal to 0.91.

When all scaling factors are very low worst case values of B is obtained as 1.23.

Hence value of B varies from 0.91 to 1.23.



Similar Reads

Difference between COCOMO 1 and COCOMO 2
COCOMO 1 Model: The Constructive Cost Model was first developed by Barry W. Boehm. The model is for estimating effort, cost, and schedule for software projects. It is also called as Basic COCOMO. This model is used to give an approximate estimate of the various parameters of the project. Example of projects based on this model is business system, p
2 min read
Advantages &amp; Disadvantages of COCOMO Model
Overview :Cocomo stands for Constructive Cost Model is a regression model based on LOC, i.e number of Lines of Code. COCOMO model is proposed by Boehm in 1981 It is a procedural cost estimate model for software projects and often used as a process of reliably predicting the various parameters related to making a project such as size, effort, cost,
3 min read
Difference Between Organic, Semi-Detached and Embedded Modes in COCOMO Model
Pre-requisites: COCOMO Model Software is a program or set of programs containing instructions that provide desired functionality. And Engineering is the process of designing and building something that serves a particular purpose and finds a cost-effective solution to problems. Cocomo (Constructive Cost Model) is a regression model based on LOC, i.
2 min read
Differences Between the Basic, Intermediate, and Detailed COCOMO Model
In the realm of software engineering, the Construction Cost Model (COCOMO) is a significant technique for estimating software costs that has been used for many years. To estimate the time, effort, and resources needed for software development to be successful, COCOMO offers an organized method. For better decision-making, enhanced project planning,
4 min read
COCOMO Model-Software Engineering
COCOMO-II is the revised version of the original Cocomo (Constructive Cost Model) and was developed at the University of Southern California. It is the model that allows one to estimate the cost, effort, and schedule when planning a new software development activity. Sub-Models of COCOMO Model 1. End User ProgrammingApplication generators are used
2 min read
COCOMO Model - Software Engineering
The Constructive Cost Model (COCOMO) is a software cost estimation model that helps predict the effort, cost, and schedule required for a software development project. Developed by Barry Boehm in 1981, COCOMO uses a mathematical formula based on the size of the software project, typically measured in lines of code (LOC). Table of Content What is th
15+ min read
Application Composition Estimation Model (COCOMO II | Stage 1) - Software Engineering
Application Composition Estimation Model allows one to estimate the cost, and effort at stage 1 of the COCOMO II Model. In this model, size is first estimated using Object Points. Object Points are easy to identify and count. Object Points define screen, reports, and third-generation (3GL) modules as objects. Object Point estimation is a new size e
4 min read
Difference between Agile Model and V-Model
Agile Model: Agile Model is the software development model in which the development and testing process carries on simultaneously. In this model, both development-related processes and testing-related processes are parallel. This model provides the facility for more interaction between the development team, testing team, and end-users. V-Model: V-M
2 min read
Difference between Prototype Model and RAD Model
1. Prototype Model : The prototype model is a software development life cycle model which is used when the customer is not known completely about how the end product should be and its requirements. So in this model, a prototype of the end product is first developed by the developers and then tested and changes were made as per customer feedback unt
2 min read
Difference between RAD Model and Incremental Model
1. RAD Model: RAD model refers to Rapid Application Development and it is a type of Incremental Model. The components or functions are developed in parallel and it can handle small projects as well as medium projects. In this model, any changes can be made at any stage. It has high productivity due to less number of people. 2. Incremental Model: In
2 min read
Difference between V-model and RAD model
1. V-model: V-model is the most important model that is used in the process of software testing. It is also known as Verification and Validation Model. It is Introduced by the late Paul Rook in the 1980s. V-model is a sequential process in which the next phase begins only after the completion of the present phase. In this model, steps don’t move in
3 min read
Difference between V-model and Incremental model
1. V model: V-model is the most important model that is used in the process of software testing. It is also known as Verification and Validation Model. It is Introduced by the late Paul Rook in the 1980s. V-model is a sequential process in which the next phase begins only after the completion of the present phase. In this model, steps don’t move in
3 min read
Difference between Lean Development Model and Agile Development Model
1. Lean Model: Lean is one of the efficient methodology that believes the flow of value to the customer through continuous improvements and value for the customer. It optimizes the available resources to create a stable workflow keeping the customer’s demand at its center. The Lean Model was first used in 1915, by Henry Ford in the Ford Motor Compa
4 min read
Difference between Agile Model and Iterative Model
1. Agile Model: Agile is a replacement for the traditional waterfall model for the creation of software development. It was developed in the year 2001 by a group of software developers for better ways for developing one. This mechanism divides the product into small builds and these small builds are developed with proper designing, coding, and test
3 min read
Difference between Waterfall model and Prototype model
Comparison of the waterfall model with the prototype model. Many people today think that both of these strategies are obsolete and should be sent to history's trash. This is untrue, though, because there are still instances in which one strategy is more practical and appropriate than another. Having a clear understanding of the variations between t
5 min read
Why Spiral Model is called Meta Model?
The Spiral Model is a well-known and widely used software development model. It has a unique approach to handling the complexities of software development, which sets it different from other models like Waterfall or Agile. It encapsulates the essence of other software development models while providing a flexible framework for iterative and risk-dr
3 min read
Why Spiral Model is Better than Waterfall Model?
The spiral model is mainly used in the development processes of complex projects while the Waterfall model is used for simple projects. Both of these models are selected as per the characteristics of the project. The risks during the project are handled by using the Spiral model and it may be considered better than the waterfall model. Also, we wil
5 min read
Pham-Nordmann-Zhang Model (PNZ model) - Software Engineering
Pham Nordmann Zhang (PNZ) model is used to evaluate the reliability prediction of a component-based system or software and fault tolerance structures techniques.PNZ is considered to be one of the best models, which is based on the nonhomogeneous Poisson process(NHPP). Our goal is to produce a reliability prediction tool using PNZ models based on re
7 min read
Difference between V-model and Waterfall model
In the software business, the Waterfall model and the V-Model are both highly popular development approaches. Both of these paradigms provide systematic assistance for the creation of apps. The primary distinction between the V-Model and the Waterfall Model is that the V-Model identifies flaws during the testing phase, whereas the Waterfall Model i
5 min read
Difference between Waterfall Model and Spiral Model
The waterfall model and Spiral model are used in software development. Waterfall model is also known as the classical or linear model because it follows sequential stages while the spiral model does not follow the sequential stages it follows the evolutionary way. The amount of risk in the waterfall model is more as compared to the spiral model bec
3 min read
Difference between RAD Model and Waterfall Model
The waterfall model is a linearly sequential life cycle model of software development in which software testing is carried out after all coding steps have been completed. This is the most fundamental distinction between the waterfall model and the RAD model. Rapid Application Development (RAD), on the other hand, uses an incremental approach to sof
4 min read
Difference between V-model and Spiral model
V-Model and Spiral Model both are software development life cycle models. The V-Model is a sequential software development model with concurrent development and testing phases, best for projects with clear requirements and low complexity. On the other hand, the Spiral Model is an iterative, risk-driven approach that handles high complexity and allo
3 min read
Difference between Spiral model and Incremental model
The Spiral Model and Incremental Model both are software development life cycle models. The Spiral Model is a risk-driven software development model that handles risks early and can manage large projects but is expensive and requires a large team. On the other hand, the Incremental Model develops the product in smaller, manageable modules with easi
3 min read
Difference between Waterfall model and Incremental model
The Waterfall Model follows a strict, linear sequence of phases and is best for small projects with well-defined requirements. It produces the final product only after all phases are completed. The Incremental Model develops the software in smaller, iterative cycles, delivering a working version early and adding features incrementally. This approac
3 min read
Difference between RAD Model and Spiral Model
Rapid Application Development (RAD) model and Spiral Model both are software development life cycle model. The Spiral Model is best for large, complex projects with significant risks, requiring detailed planning and extensive documentation, while the RAD Model focuses on rapid development with easy changes, using smaller teams and minimal planning,
3 min read
Difference between Prototype Model and Incremental Model
The Prototype Model focuses on creating a preliminary version of the software to refine based on user feedback, ideal for projects with unclear requirements. The Incremental Model builds the software in small, manageable sections, adding functionality in each cycle, suitable for projects needing steady progress and user involvement throughout. What
3 min read
Difference between Prototype Model and Spiral Model
The Spiral Model and Prototype Model are two distinct approaches in software development. The Spiral Model focuses on managing risks through iterative cycles, integrating elements from incremental and evolutionary prototyping. In contrast, the Prototype Model emphasizes rapid development and continuous customer feedback to refine the product until
5 min read
Metrics for the Design Model of the Product
Metrics measures quantitative assessment that focuses on countable values most commonly used for comparing and tracking the performance of a system. Metrics are used in different scenarios like analyzing models, designing models, source code, testing, and maintenance. This article focuses on discussing metrics for the design model of the product. T
12 min read
Difference between Good Design and Bad Design in Software Engineering
The term design is used in two ways. While used as verb, it means - the design process and used as noun, it means- the result of design process. Design is a meaningful engineering representation of something that is to be built. The result of a design process is called as design model or the design of the system. Design for computer software is as
2 min read
Difference Between Technical Design and Conceptual Design in Software Engineering
What is Software Design?Software design is a process to convert the user requirements into client requirements user interface form, that helps the software developer in coding and implementation. The software design deals with portraying the client's requirement which is described in Software Requirement Specification (SRS) document into a user int
3 min read
Article Tags :