GATE | GATE CS 1996 | Question 45
Four jobs to be executed on a single processor system arrive at time 0 in the order A, B, C, D. Their burst CPU time requirements are 4, 1, 8, 1 time units respectively. The completion time of A under round robin scheduling with time slice of one time unit is
(A) 10
(B) 4
(C) 8
(D) 9
Answer: (D)